Penn Yan’s Main St. Revitalization Work to Resume

SHARE NOW

The village of Penn Yan says its Main Street revitalization work will begin next week.

Work is scheduled to start Tuesday and is estimated to take 4-6 weeks to complete. The project will include curbing, sidewalks and paving from Elm Street to Clinton Street. During this time, Main Street will be closed from Elm Street to Maiden Lane with weekend closures as needed.

Residents who have any questions are urged to reach out to the village’s Department of Public Works. If you have questions please call their office at 315-279-6535.

MAIN STREET RESTORATION:
???????????????????????????????????? ???????????? – Site layout and utility stakeout work will begin – Main Street will remain open to traffic
???????????????????????????????????? ???????????????? – Road boxout will begin – Main Street will be closed to traffic from Elm Street to Maiden Lane
Businesses will remain open during construction.